Zilker: That’s a lot of dillo dirt!

AustinParksFoundationParks, Special Projects Leave a Comment

Over a week ago (12.27.08), the Parks department began work on the big Zilker irrigation project -essentially leveling the site, installing 17,000 feet of irrigation pipes and 42 acres of sod!  The first big project is to add soil amendments – in this case, Dillo Dirt – a compost blend made by the city with yard waste trimmings and composted …

Republic Update: 1/5/09

AustinParksFoundationSpecial Projects, Parks Leave a Comment

Happy belated New Year to all! A quick update on our Auction Oaks project – the path installation is nearly complete and we’re working to get the right big trees installed – a big red oak should be planted shortly along with another four trees shortly there after.  Then its irrigation, seeding and the stone bollards and chain enclosure.  More …

12/16: Tree Planting at Republic

AustinParksFoundationParks, Special Projects Leave a Comment

[fusion_builder_container hundred_percent=”yes” overflow=”visible”][fusion_builder_row][fusion_builder_column type=”1_1″ background_position=”left top” background_color=”” border_size=”” border_color=”” border_style=”solid” spacing=”yes” background_image=”” background_repeat=”no-repeat” padding=”” margin_top=”0px” margin_bottom=”0px” class=”” id=”” animation_type=”” animation_speed=”0.3″ animation_direction=”left” hide_on_mobile=”no” center_content=”no” min_height=”none”] Beginning late last week, tree transplanting and planting began.  Enviromental Design moved two good sized “understory” trees from their locations on the edge of the former western berm over to the eastern side of the park …

12/11 Republic Square Project Update

AustinParksFoundationSpecial Projects, Parks Leave a Comment

Over the past few days, the work at Republic Square has been less visible, but it’s still going on with lots more grading around the site, silt fence installation, digging out of the granite gravel path and the beginning of transplanting of two trees that are currently located on the edge of the (almost) former western berm.  An Environmental Design …

Day 5: Grading / Berm work complete

AustinParksFoundationSpecial Projects, Parks Leave a Comment

[fusion_builder_container hundred_percent=”yes” overflow=”visible”][fusion_builder_row][fusion_builder_column type=”1_1″ background_position=”left top” background_color=”” border_size=”” border_color=”” border_style=”solid” spacing=”yes” background_image=”” background_repeat=”no-repeat” padding=”” margin_top=”0px” margin_bottom=”0px” class=”” id=”” animation_type=”” animation_speed=”0.3″ animation_direction=”left” hide_on_mobile=”no” center_content=”no” min_height=”none”] As of Friday, Dec 5th, the berm removal and rough grading work is complete.  the western berm (along San Antonio St) was completely removed and the the southern berm (along 4th St) was slimmed down considerably. …

Day 4: Western Berm is gone

AustinParksFoundationParks, Special Projects Leave a Comment

Today (12/4) our contractors completed removal of the western (along San Antonio St) berm, save a small area where there are two small trees awaiting transplanting next week.  So, work has shifted to shaving down about half of the southern (along 4th St) berm.  Looking good! [fusion_builder_container hundred_percent=”yes” overflow=”visible”][fusion_builder_row][fusion_builder_column type=”1_1″ background_position=”left top” background_color=”” border_size=”” border_color=”” border_style=”solid” spacing=”yes” background_image=”” background_repeat=”no-repeat” padding=”” …