The last pieces of the deck around the future tree grate are being installed as well as the set of limestone facing pieces along the flush (ADA) portion of the deck.

Much of the mulch has been spread under the auction oaks and the Decomposed Granite walkway is beginning to get formed with steel edging going in.  All lights are installed and have passed inspection.

Large pallets of sod are awaiting the completion of final grading work. We hope to do a punch list walk-through Wednesday afternoon.  So, so close!