With a grant from the Austin Parks Foundation and a lot of fundraising by the Hill Country Inline Club, there is now a great new shelter at the entrance to the Veloway with benches where folks can put on their skates, take a break between cycling and skating activities. These photos are from Hill Country Inline members.
Republic-Concrete Beam Forming
Work has began on forming up the concrete beams that will hold the deck around the perimeter. The western beam will be elevated, sitting on the piers, while the eastern berm will be flush with the ground. We hope to pour the beams by Wednesday or Thursday. Meanwhile, White Construction Co. is excavating madly at the courthouse site across San …
Republic – Footings complete!
Our Lansdscape subcontractor, Cleanscapes, has finished the pouring of the four final piers for our 4,000 square foot deck project at Republic Square. All told, it took three weeks of work (using very careful approaches) to dig, prepare and pour 22 footings. The interior 12 footings are 3 foot by 3 foot by 3 foot holes with a 3 foot …
Republic: 5 footings to go
17 out of the 22 footings for the deck project have now been poured, 5 to go and we hope to pour them on Thursday. Then, we start forming up the outer berms that will form the outer backbone of the deck. It will start looking like a deck soon!
Oyster Boot Camp @ Republic
23 people came out for the free Oyster Boot Camp, a trial run of the Austin Oyster Adventure Race scheduled for October 11th. While I was there, I snapped a photo of the sign for our Auction Oaks deck project. Folks at the Boot camp did the following: 1) Obtained 24 coffee beans. 2) Biked and took photos of either …
Rooted At Republic
Excavation with Air Spade and shovels continues at Republic Square. Here’s a few photos from today. This first photo shows a web of roots, but we can still put a pier in the middle that will avoid all of those roots. The second photo shows a larger outside pier location (hole) that has only a few well positioned roots, already …
Piers Around Roots
We’ve now poured 7 of the 11 internal piers for the deck at Republic Square and this photo shows how we’re doing it, we are moving the pier locations to adjust for the roots that we find. We wrap the roots in burlap to keep them moist and protected. Once the concrete hardens (tomorrow) we’ll backfill with soil.
View From Above
Thanks to Greg Anderson for today’s (09/02/09) view of Republic Square from the 360 Condos. the former souther berm site is looking pretty green, you can see the work going on under the central auction oak, as well as the courthouse ground breaking ceremony tent. [fusion_builder_container hundred_percent=”yes” overflow=”visible”][fusion_builder_row][fusion_builder_column type=”1_1″ background_position=”left top” background_color=”” border_size=”” border_color=”” border_style=”solid” spacing=”yes” background_image=”” background_repeat=”no-repeat” padding=”” margin_top=”0px” …
Veloway Video
The Veloway [fusion_builder_container hundred_percent=”yes” overflow=”visible”][fusion_builder_row][fusion_builder_column type=”1_1″ background_position=”left top” background_color=”” border_size=”” border_color=”” border_style=”solid” spacing=”yes” background_image=”” background_repeat=”no-repeat” padding=”” margin_top=”0px” margin_bottom=”0px” class=”” id=”” animation_type=”” animation_speed=”0.3″ animation_direction=”left” hide_on_mobile=”no” center_content=”no” min_height=”none”][youtube=http://www.youtube.com/watch?v=3YCfnuGqs5w] We just got a new video camera, and I tested it out at the Veloway. Forgive the rough cuts – it’s my first time w/the editing software, too.[/fusion_builder_column][/fusion_builder_row][/fusion_builder_container]
Republic – 4 piers poured on Monday
On Monday the first four piers were poured with 7 more in the interior area to go. These are three feet deep with a one foot thick footer and either 12 inch or 16 inch diamter column at the center. A picture from yesterday afternoon shows the tubes in place prior to the concrete pour and another perspective shot looking …